Early Electrification Of Buffalo: Niagara Falls Hydraulic Development - Adams Station
From GHN
(Difference between revisions)| Line 1: | Line 1: | ||
| − | ‘Fast tracking’ a building where the foundation is completed before the design of the upper floors is complete is a common current practice. This principle was applied to construction of the Adams Station. Because a tailrace tunnel was common to any project, | + | ‘Fast tracking’ a building where the foundation is completed before the design of the upper floors is complete is a common current practice. This principle was applied to construction of the Adams Station. Because a tailrace tunnel was common to any project, a contract was awarded in September 1890. Construction of the 1-1/4 mile long tunnel[[Image:04_Tailrace_Tunnel_-_cropped.GIF|thumb|left|Tailrace Tunnel]] commenced in October 1890 and was completed in December 1892. A horseshoe shape 21 feet high and 18.8 feet wide[[Image:04_Tunnel_Cross_Section_-_cropped.GIF|thumb|right|Tunnel Cross Section]] was selected. During construction through the weak Rochester shale strata, it became necessary to line the tunnel using a total of sixteen million bricks in four courses set in Portland cement.[[Image:04 Tailrace Tunnel Profile.GIF|thumb|right|210x175px]] A profile of the tunnel shows the extent of the shale. |
By July 1891 plans had reached the following stage: [[Image:04 July 1891.GIF|thumb|left|210x175px]] <br> | By July 1891 plans had reached the following stage: [[Image:04 July 1891.GIF|thumb|left|210x175px]] <br> | ||
| Line 29: | Line 29: | ||
[[Image:04-53 powerhouse no.1.GIF|thumb|right|210x175px]]The New York City architectural firm of McKim, Mead & White was engaged to design the limestone powerhouse. | [[Image:04-53 powerhouse no.1.GIF|thumb|right|210x175px]]The New York City architectural firm of McKim, Mead & White was engaged to design the limestone powerhouse. | ||
| − | <br> <pageby | + | <br> <pageby comments="false" nominor="false"></pageby>; |
<br> | <br> | ||
Revision as of 19:47, 15 September 2008
‘Fast tracking’ a building where the foundation is completed before the design of the upper floors is complete is a common current practice. This principle was applied to construction of the Adams Station. Because a tailrace tunnel was common to any project, a contract was awarded in September 1890. Construction of the 1-1/4 mile long tunnel commenced in October 1890 and was completed in December 1892. A horseshoe shape 21 feet high and 18.8 feet wide was selected. During construction through the weak Rochester shale strata, it became necessary to line the tunnel using a total of sixteen million bricks in four courses set in Portland cement. A profile of the tunnel shows the extent of the shale. By July 1891 plans had reached the following stage:1. Hydraulic system consisting of a single inlet canal, the shortest possible tailrace tunnel, and a central station for power development. The turbine units should be large and mounted at the bottom of the wheel pit. Their complementary machines, whether pumps, compressors or generators should be mounted on the top of the same rotating shaft so as to constitute a unit of power.
2. Local distribution of power by direct current of electricity.
3. Transmission of power to Buffalo by compressed air.
The inlet canal was started in August 1891 and completed in October 1892. The 20 feet wide and 182 feet deep stone masonry wheel pit was started in late 1891 and completed in January 1894.The state of the art of electric power transmission in the early 1890’s was as follows:
1. 1890 - Willamette Falls to Portland, Oregon - 4,000 volts ac single-phase 12 miles for lighting.2. 1891 - Telluride, Colorado - 3,000 volts ac single-phase three miles supplying a 100-hp synchronous motor for operating an ore crushing plant.
3. 1891 - Lauffen to Frankfurt, Germany - Experimental 30,000 volt three-phase line 108 miles for 300 hp for the Frankfort Exposition. Overall efficiency 77 percent.
In early autumn of 1891 it became evident that alternating current could be safely and economically controlled for the transmission of power more than five times the distance from Niagara to Buffalo. From this period, all serious attention was concentrated upon electrical installations; generators, transformers, transmission lines, motors, and power and light distribution.
In December 1891 an invitation to submit proposals for generation of electrical energy for local lighting and power purposes was sent to three United States and three Swiss electrical equipment designers and manufacturers. The invitation did not mention direct current, alternating current or voltage. It took a year until all proposals were received.
- Page created by Cawoody, 8 September 2008
- Contributors: Cawoody x7, Azalma x14, Vardalas x1, Nbrewer x3, Csommero x3, Kwiggins x1
- Last modified by Kwiggins, 11 June 2010
<rating comment="false"> Well Written? 1 (No) 2 3 4 5 (Yes) </rating> <rating comment="false"> Informative? 1 (No) 2 3 4 5 (Yes) </rating> <rating comment="false"> Accurate? 1 (No) 2 3 4 5 (Yes) </rating>
